Apply 'Job Cycle Time' to Crews

By Brad Humphrey
Contributing Writer

Pavement, September 2006

Last issue we introduced you to "job cycle time," urging you to identify the steps each job requires and offering some insights into how you might approach determining cycle times for the work you do. In this issue we'll help you get a time study done so you can apply job cycle time to your business.

Completing a time study is not difficult. Using a stopwatch, record the beginning time you or your crew begins a particular step and the completion time. To provide you with some level of confidence about the cycle time of a process step, you should measure the same process step on several jobs and then take the average of the times recorded. Once you are confident that the average time for a particular step is secure, establish this time as your cycle time for the step or process that was timed.

One secret measuring effort I've used before is to measure the average time a paving crew can place eight tons, then 16 tons, then 32 tons etc. Having a breakdown of tonnage can then help you be more accurate, and faster, when putting estimates together. Similarly, you might measure your sealcoat crew on applying one coat per ten thousand square feet or other increments of square footage often completed.

When you are developing a cycle time standard for a process, be sure that the steps used to complete the process are the same. If you record the same process three different times, and the order of completing the process is different each time, you will potentially bias the average time arrived at. Such a miscalculation could prevent you from establishing a dependable time to base your customer bids and job scheduling on. In other words, compare lots that have no islands as an example against each other. Then, measure your crews on similar size lots with two to four islands. Bunch similar type jobs together so you are confident in the benchmarking of lots.

Cycle times can be established for any process within your business. Once you have established cycle times, make sure that you inform your employees. Cycle times should become the standard operating goals for completing jobs. Therefore, when processes take longer than expected to complete, compared to the established cycle time standard, questions should be raised as to the possible causes for the additional time. Remember, time is money…I mean speed is money!

1 2 next
E-mail This StoryE-mail Article Print This StoryPrinter Friendly


Submit a Comment

Name: *
Subject:
Location:
  (display Email: )
 
 
Enter the characters you see in the image:
 
 
 
   
* = required
(comments will appear after this article, as well as on our Readers Respond Page)